Article

S.A. Management of Risk

Management of risk and contingencies, alternative scenario’s, what if …

risk-management-process.jpg

The project is depends on many actors and factors. There are certain expectations of the actors and factors. If these expectations will not be lived up, other solutions have to be found.

In the period from november to january the main actors of the project are:

  • Project owner Mr. Mofokeng
  • Financial consultant Mrs. Mofokeng
  • Student team 1
    • Roxanne Goemans
    • Len Rijvers
    • Evan Roberts
  • Student team 2
    • Yonis Le Grand
    • Steven Roerink
    • Job Seuren
    • Eva ten Velden
  • Government
  • Local contractors
  • Suppliers of biomass
  • Employees
  • Tshwane University of Technology

The factors that affect the project from november to january:

  • Car
  • Money
    • Grants
  • Permits

 

Risk

Description and action plan

Conflict between parties

Conflicts can arise from different causes and can have negative effects on the project. Different culture have different ways of thinking, so it is important the other party has be approached discreetly. For both parties the higher goal is the success of the project, so you have to make some compromises. It is essential that the communication between the parties remain good, so that conflicts can be prevented.

No grants

The funding of the government is very important for the project. The construction of the biogas plant will be partly financed by these fundings. If the farm does not get the grants, it will lead to a stagnation of the project.

If this happens, we will try to do as much as we can of that what doesn’t depend on the grants. We will have to discuss with Dr. Kroesen about the continuation plan.

No permits (in time)

If the permits will not be given in time, the construction of the biogas plant will be postponed. The only thing that can be done is the  preparation work for the construction. This includes writing the business plan, networking, approaching the Tshwane University of Technology, creating renewable energy awareness etc..

Unable to drive the car

If we are unable to drive the car, there are certain things we can do:

  1. Let us drive by a taxi or let us be driven by an acquaintance
  2. Try to borrow or buy another car

Unable to get in contact with professors

If we can not get in touch with the professors of the Tshwane University of Technology, due to holidays or other causes, we could try to get in touch with the Executive Board or other departments.

The design of the biogas plant is not ready for construction

If the design of the biogas plant is not ready in the period of november to january, the design has to be finished by another party. This could be another follow-up group or a biogas contractor.